location_on Kensington, W8, London schedule Total Duration: 24 Weeks square_foot 3,200 SQ FT

The Phillimore Gardens Residence

info About This Project

Situated in the heart of Kensington's prestigious Phillimore Estate, this Victorian villa underwent a complete architectural restoration. Our team executed a subterranean basement excavation, installed structural steel frames, and delivered high-end bespoke interior finishes while strictly adhering to Royal Borough conservation guidelines.

Finished interior of a high-spec Victorian double-fronted villa in Kensington London showcasing kitchen and marble island
Category: Refurbishments 10-Yr Guarantee
Transparent Unit Rates

Itemised Element Pricing

Unit pricing schedule for distinctive elements of the work executed on this project.

price_check Itemised Unit Rates — No Bundled Totals
payments

Hardwood Floor Supply & Precision Installation

Unit Price: £12 per square meter
payments

Wall Plastering, Skimming & Acoustic Insulation

Unit Price: £50 per square meter
payments

Subterranean Mass Concrete Underpinning

Unit Price: £180 per linear meter
payments

Structural Steel Beam Erection (RSJ Steelwork)

Unit Price: £135 per linear meter
payments

NICEIC Smart Electrical Circuit Wiring & Outlets

Unit Price: £85 per outlet point
Specification & Finishes

Materials Used

High-spec materials and products specified throughout this property build.

category Calacatta Gold Natural Italian Marble

20mm honed slabs for kitchen waterfall island & master ensuite wall cladding

Shop Link (Coming Soon) link

category Engineered Prime Grade European Oak Flooring

220mm wide plank herringbone pattern with acoustic dampening underlay

Shop Link (Coming Soon) link

category Crittall W20 Steel Glazed Doors & Partitions

Bespoke black powder-coated acoustic thermal break internal glass partitions

Shop Link (Coming Soon) link

category Lutron Homeworks QSX Lighting Control System

Architectural keypads and automated circadian lighting modules

Shop Link (Coming Soon) link
Execution Timeline

Chronological Stages

Step-by-step progression, site photos, videos, and milestone breakdown.

1
Milestone Stage 1

Stage 1: Site Setup, Conservation Approvals & Underpinning

timer Duration: 6 Weeks

Establishment of site hoardings, temporary structural propping, mass concrete bay-by-bay underpinning beneath Victorian footings, and continuous vibration telemetry monitoring.

photo_library Stage Media (Photos & Videos)

Site excavation and structural underpinning work underway in Kensington

Site excavation and structural underpinning work underway in Kensington

Video walkthrough of structural foundation excavation

2
Milestone Stage 2

Stage 2: Structural Steelwork, Waterproofing & Roof Framing

timer Duration: 8 Weeks

Installation of primary load-bearing RSJ steel frames, Newton 500 subterranean cavity drain membrane waterproofing system, and slate roof restoration.

photo_library Stage Media (Photos & Videos)

Structural steel cage and waterproof tanking system

Structural steel cage and waterproof tanking system

Timber roof joists and slate tiling installation

Timber roof joists and slate tiling installation

3
Milestone Stage 3

Stage 3: First Fix M&E, Drylining & Floor Heating

timer Duration: 5 Weeks

NICEIC first-fix electrical conduit routing, Lutron smart lighting backbone, wet underfloor heating pipework embedment, and acoustic plasterboarding.

photo_library Stage Media (Photos & Videos)

First-fix electrical cabling and manifold underfloor heating pipes

First-fix electrical cabling and manifold underfloor heating pipes

4
Milestone Stage 4

Stage 4: Luxury Joinery, Marble Tiling & Final Commissioning

timer Duration: 5 Weeks

Installation of bespoke architectural joinery, Calacatta marble wall panels, heritage gold brassware, and smart home lighting commissioning.

photo_library Stage Media (Photos & Videos)

Completed interior showing marble island and custom cabinetry

Completed interior showing marble island and custom cabinetry

Finished herringbone oak flooring and mood lighting details

Finished herringbone oak flooring and mood lighting details

Expert Advice & Guidance

Prerequisites & Expert Advice Before Starting Similar Renovations

Planning a comprehensive structural renovation or basement expansion in London requires careful regulatory and logistical preparation before breaking ground.

gavel

Party Wall Agreements & Boundary Surveying

Serve formal Party Wall notices to all adjoining property owners at least 2 to 3 months prior to excavation. Ensure a Schedule of Condition is completed.

architecture

Structural Calculations & Soil Hydrology

Commission a structural engineer for steel beam loading calculations and soil borehole testing before specifying foundation depth.

Project Clarifications

Questions & Answers

Frequently asked questions regarding this specific London project execution.

help_outline Was planning permission required for this Kensington villa transformation? expand_more

Yes. Because the property is located within a Royal Borough Conservation Area, full planning permission was obtained alongside formal Royal Borough of Kensington and Chelsea (RBKC) design sign-off.

help_outline How did you manage structural stability and neighbor noise during excavation? expand_more

We installed real-time telemetry vibration sensors on shared party walls and executed underpinning in strict 1-meter bay sequences under chartered structural engineer oversight.

Inquire For Your Property

Request Site Feasibility for a Similar Build

Interested in achieving similar results for your London home? Speak with our surveying team.